Skip to content
Menu

The Macau Bridge will open to traffic in the third quarter of this year

The final stages of work being carried out on Macau Bridge are set to be finalised this month and the structure will be ready for vehicles shortly after
  • The bridge, built at a cost of 5.46 billion patacas (US$680 million), is designed to improve traffic flows between the peninsula and Taipa

ARTICLE BY

PUBLISHED

ARTICLE BY

PUBLISHED

UPDATED: 02 Jul 2024, 7:41 am

The Macau Bridge will be open to traffic in the third quarter of this year, according to the Public Works Bureau (known by its Portuguese initials DSOP). 

The final stages of work were expected to be wrapped up this month. Once finished, the DSOP said the 3.1 kilometre, eight-lane bridge’s temporary support structures would be “dismantled immediately.”

The bureau also noted that the bridge’s asphalt had been successfully laid by a construction team working “day and night.” 

[See more: Officials defend the name ‘Macau Bridge’]

Despite challenges brought about by April and June’s unusually wet weather, the team managed to finish asphalting 117,000 square metres of the bridge’s surface in just 102 days – three days faster than planned.

When it’s up and running, the bridge will improve traffic flows between the peninsula and Taipa. It connects the yet-to-be-named reclamation areas known as Zone A and E1.

It took four years and around 5.46 billion patacas (US$680 million) to build the Macau Bridge. A panel of judges settled on its name in March, from a shortlist of options suggested by residents.

UPDATED: 02 Jul 2024, 7:41 am